Problem 798

Daily Math Challenge - September 28, 2022



A construction company used 20 workers to complete one-fourth of a construction job in 8 days.  Then, because of weather it became necessary to complete the remainder of the job in the next 5 days.  How many additional workers were added to the crew of 20 to accomplish and complete the job?